Apa sudah jadi dgn Putrajaya Monorel?

Monorel Putrajaya
Dari Wikipedia Bahasa Melayu, ensiklopedia bebas.
(Dilencongkan dari Putrajaya Monorail)

Monorel Putrajaya atau Putrajaya Monorail merupakan sebuah monorel di Putrajaya yang sedang dalam pembinaan. Pada asalnya Putrajaya dirancangkan untuk mempunyai sebuah sistem aliran ringan, malah terowong untuk sistem ini telah dijalankan, tetapi selepas rancangan ditukar, rancangan monorel terpilih. Monorel ini dicadangkan mempunyai dua aliran - satu sepanjang 12 km dengan 17 buah stesen, satu lagi sepanjang 6 km dengan 6 buah stesen.[1] Pembinaan ini terhenti pada tahun 2004, dan mungkin akan diteruskan selagi bandar ini bertambah bilangan penduduk.[2] Monorel ini akan termasuk Monorail Suspension Bridge, kini masih belum siap,[3] dan Jambatan Putra.[4] Jambatan ini akan bersambung dengan stesen ERL Cyberjaya/Putrajaya. Kos projek ini adalah sebanyak RM400 juta.[5]

Putrajaya Monorel
Putrajaya Monorail

Jumlah stesen: 23
Jenis: Monorel
Jarak Aliran: 18 km
Kawasan Perkhidmatan: Presint 11 - Presint 3 - Presint 1 - Presint 14 - Presint 17 - Presint 6

http://ms.wikipedia.org/wiki/Putrajaya_Monorail
 
ARKIB : 09/06/2004
Putrajaya monorail project postponed

PUTRAJAYA June 8 - The 9 km long monorail project in Putrajaya,the federal administrative capital,has been postponed, Minister of the Federal Territories Tan Sri Mohamed Isa Abdul Samad said Tuesday.

The monorail transportation system development was included in Putrajaya's masterplan and was also part of the federal administrative capital's integrated transportation system.

However some office development projects in Putrajaya and those that had been completed had not been occupied and the monorail was to have served these areas.

Once these buildings were completed and occupied the monorail project could then resume, he said.

"Around the `Core Island' area for instance, we have targetted a 30 percent occupancy rate and we also want the two new ministry buildings to be fully completed and occupied before the monorail can move in," he told reporters when asked on on the status of the RM400 million monorail project, which was initially scheduled to be completed by year-end.

He declined to comment when asked if the financial factor was among the reasons for the postponement.

Earlier, Mohamed Isa accompanied by Putrajaya Corporation President, Tan Sri Azizan Zainul Abidin toured the `Core Island' which encompassed the Boulevard, Putra Square and the two new ministry buildings which were nearing completion.

http://www.utusan.com.my/utusan/inf...pub=Utusan_Express&sec=Home_News&pg=hn_06.htm
 
pasal corruption la semua projek x jadi..so ada b end ambil kisah?...diaorang dah siap2 makan komisyen..ape nak kisah...:))
 
diorang tau kalau buat pun bukan ramai penduduk nak guna dan for sure tak balik untung.
 
akan disambung monorel selepas pru13 bilamana pakatan rakyat ambil alih putrajaya ...amin ya robbalalamin
 